Summary
Omega Technical Services' involvement was crucial in ensuring the successful conversion and commissioning of the FastLNG 1 facility. Our comprehensive engineering support and commissioning services contributed significantly to New Fortress Energy's goal of creating a flexible, rapidly deployable LNG production solution. This project showcases our capability in supporting cutting-edge developments in the LNG industry, particularly in the realm of modular and offshore liquefaction technologies.
Key Feature
- Conversion of a Jack-up Drilling Unit into a three-platform Liquefaction – Storage – Offloading facility
Project Scope
- Development of a Fast LNG modular liquefaction facility
- Capacity: 1.4 MM-metric ton (1.54-MM ton)
Modular Liquefaction Technology:
- Utilizes latest advances in mid-size liquefaction technology
- Designed for lower cost and faster deploymen
Repurposed Infrastructure:
- Conversion of jackup rigs or similar floating infrastructure
- Enables deployment in various locations with stranded natural gas resources
Storage Solution:
- Permanently moored Floating Storage Unit (FSU) alongside the liquefaction infrastructure
- Operates as an LNG storage facility
Key Advantages
- Flexibility to deploy anywhere with large volumes of stranded natural gas
- Faster deployment schedule compared to traditional LNG facilities
- Cost-effective solution for monetizing stranded gas resources
Services Provided
Omega Technical Services provided crucial support to the FastLNG 1 project:
- Marine Systems Engineering and Conversion Support:
- Conducted detailed engineering for the conversion of the jack-up drilling unit
- Designed integration systems for the three-platform configuration (Liquefaction, Storage, Offloading)
- Provided technical support for marine systems adaptation to LNG production and handling
- Ensured compliance with maritime regulations and LNG industry standards
Commissioning Planning:
- Developed comprehensive commissioning strategies for the converted facility
- Created detailed plans for integrating modular liquefaction units with the repurposed jack-up rig
- Established timelines and milestones for the commissioning process
- Designed safety protocols specific to the unique configuration of the FastLNG facility
Commissioning Execution:
- Oversaw the implementation of commissioning plans
- Coordinated between various teams to ensure smooth integration of all systems
- Managed the testing and validation of newly installed liquefaction equipment
- Supervised the startup procedures for the integrated Liquefaction-Storage-Offloading facility
Throughout these services, Omega Technical Services demonstrated:
- Expertise in offshore facility conversion and LNG systems integration
- Ability to manage complex, innovative projects combining multiple technologies
- Commitment to safety and environmental standards in challenging offshore environments
- Skill in optimizing commissioning processes for rapid deployment of LNG facilities